artistic render of high park station post-construction
Easier Access Program

High Park Station

Project Update

Easier Access

Construction at High Park Station has begun and will be completed by the end of 2024.

cross section of new elevators at high park station

Cross section image of station elevators

This work will include:

  • Two new elevators, one to each subway platform
  • Improved signage
  • CCTV - security cameras installed inside the station
  • New main entrance structure and automatic sliding doors

What to expect:

During construction:

  • Quebec Avenue entrance closed for duration of construction. All customers will be redirected to the Parkview Gardens and High Park Avenue entrances.
  • Buses maintained inside the station, subway service maintained
  • No Wi-Fi at street level, only at concourse and subway platform level
  • Benches at street level relocated
  • Bike rings on Quebec Avenue removed and restored at end of project. Bike parking on High Park Avenue maintained.

 

Traffic, pedestrian and cyclist details

  • During early phases of construction, a lane reduction in front of the main entrance on Quebec Avenue will be required.
  • The sidewalk in front of the station will be closed during construction.
  • Customers will be redirected to the Parkview Gardens and High Park Avenue entrance to access the station.
After construction:

Artistic rendering of High Park Station (Quebec Avenue entrance) after construction

Work hours

Work will typically take place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends between 9 a.m. and 7 p.m. may be required. For safety, overnight work may be required. 

TTC service
Access to the station, bus and subway service will be maintained throughout construction.

 

Project documents

For further information:

Nick Chan
Senior Community Liaison
416-931-6754
nick.chan@ttc.ca 

 

Easier Access Program

  • Program overview

    TTC’s Easier Access Program will make all subway stations accessible to everyone, regardless of their level of mobility. Today, more than half of our stations are accessible to people with disabilities. Learn more about the complete schedule.

  • Station Completion Schedule

    Schedule for all stations to be completed by 2025, as required by Provincial AODA Legislation, based on full funding.

    Stations

    Complete in

    Lansdowne 2022
    Donlands 2022
    Spadina 2024
    College 2023
    Lawrence 2024
    Greenwood 2023
    Christie 2023
    Castle Frank 2023
    Summerhill 2023
    High Park 2024
    King 2024
    Museum 2024
    Rosedale 2024
    Old Mill 2024
    Glencairn 2024
    Warden 2024
    Islington 2024

    All schedules are subject to change.

Contact us

If you are interested in receiving updates about this project, please email your contact information to the project's Community Liaison Officer.

Please be sure to include your name, address (including city and postal code), phone number and email address. Also, please let us know how you prefer to be contacted – by email, regular mail or both.

Nick Chan
Senior Community Liaison Officer
Nick.Chan@ttc.ca
(416) 931 - 6754

Construction notices

For construction updates on this project, see the Construction Advisory page.

Alternatively, email nick.chan@ttc.ca to be added to the mailing list.