Museum Station
Easier Access
Construction at Museum Station has begun and will be completed by the end of 2024.
Rendering of the Museum Station Second Exit/Entrance, looking north towards the War Memorial.
Cross section image of station elevators
What we are doing and why
Construction work will occur concurrently to build two new elevators and a new second entrance/exit at the north end of Queen’s Park. By the end of 2024, the station is scheduled to be fully accessible and the new entrance/exit will improve customer safety and convenience.
Phase 1B – December 2022 to Q2/Q3 2023
- Two construction work zones will be active during the initial phase of this project.
- Elevator construction and structural rehabilitation will take place south of Bloor Street.
- Second Entrance/Exit construction will take place at the north end of Queen’s Park Circle.
- The major work activities will include shoring and excavation.
- Two traffic lanes will be maintained: one southbound, one northbound.
Traffic, cyclist and pedestrian details
- Queen’s Park lane restrictions will be in effect between south of Bloor Street to the north end of Queen’s Park Circle.
- Minimum of one lane in each direction through the work zones will be maintained at all times.
- A cycling detour is being maintained around the construction work zones Pedestrian travel around the work zones will be maintained.
Work hours
- Work will typically take place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends and overnight may be required.
TTC service
Subway service at the station will be maintained throughout construction.
Project documents
Easier Access Program
-
Program overview
TTC’s Easier Access Program will make all subway stations accessible to everyone, regardless of their level of mobility. Today, more than half of our stations are accessible to people with disabilities. Learn more about the complete schedule.
-
Station Completion Schedule
Schedule for all stations to be completed by 2025, as required by Provincial AODA Legislation, based on full funding.
Stations
Complete in
Lansdowne 2022 Donlands 2022 Spadina 2024 College 2023 Lawrence 2024 Greenwood 2023 Christie 2023 Castle Frank 2023 Summerhill 2023 High Park 2024 King 2024 Museum 2024 Rosedale 2024 Old Mill 2024 Glencairn 2024 Warden 2024 Islington 2024 All schedules are subject to change.
Contact us
If you are interested in receiving updates about this project, please email your contact information to the project's Community Liaison Officer.Please be sure to include your name, address (including city and postal code), phone number and email address. Also, please let us know how you prefer to be contacted – by email, regular mail or both.
Nick Chan
Senior Community Liaison Officer
Nick.Chan@ttc.ca
(416) 931 - 6754
Construction notices
For construction updates on this project, see the Construction Advisory page.Alternatively, email nick.chan@ttc.ca to be added to the mailing list.